A83

"Flow down of engineering specification requirements only applies to Lockheed Martin designed parts. Unless a particular revision of an engineering specification document is listed, use only the latest revision of the revision in effect on the date of the contract. The requirements of these documents are hereby incorporated into this PO by this reference as applicable to respective programs:

1. EMAP database requirements (applicable to all programs except F-16, F-2 and T-50) are located on the Lockheed Martin external web page at http://www.lockheedmartin.com/aeronautics/materialmanagement/ under 'Engineering' then 'Engineering Materials and Approved Products'

2. Applicable program and lm aero engineering specifications are located at http://www.lockheedmartin.com/aeronautics/materialmanagement/ under 'Engineering' then 'Material & Process Specifications – All Programs'

3. Marietta programs only: C-130, C-27, C-5, P-3, S-3, F-22

For parts listed on Lockheed Martin engineering drawings, one of the following will be required:

  • Preferred Parts Handbook (PPH) volumes 1-5
  • Design Support Database: DSD – parts core Marietta programs (formerly known as Preferred Parts Handbook - PPH vol 6 section 99) applicable to all Marietta programs except F-22
  • Design Support Database: DSD – parts F-22 program (formerly known as Parts Procurement Manual - PPM) only applicable to F-22 program
  • The Preferred Parts Handbook (PPH), volumes 1-5, is not on-line and must be obtained from the buyer. The Balance of the Bulleted Items are on-line and must be obtained from the Lockheed Martin external web page at http://www.lockheedmartin.com/aeronautics/materialmanagement/ under 'Engineering' then 'Engineering Materials and Approved Products'

    Seller hereby agrees that (1) it has obtained or will timely obtain the latest applicable program specification document as referenced above, and (2) in performance of its obligations in connection with this PO, seller shall comply with such specification documents and all other requirements of this PO, unless seller is otherwise directed by buyer.

    Engineering Specification Requirements are Lockheed Martin Corporation Proprietary Information and as such are protected in accordance with the PIA executed to gain access to the systems.

    Seller shall flow down the applicable Lockheed Martin specifications and approved materials to each sub-tier involved with producing the Lockheed Martin designed part."