Pre-System Startup Operations in Process


01-28-13-1340-front-entance-overview-cw

Friday, February 9, 2013

 
Pre-System Startup Operations in Process

 

Pre-system startup operations began this week on the Lockheed Martin Facility with operator training, continued testing of process equipment, instrument communications systems and extraction well pumps.

In the field, crews continued addressing minor punch list items at well vault and control panel locations. Field crews will soon be demobilizing.   

Next week, building crews will continue with pre-system start-up testing, testing process equipment and communications systems, operator training, and addressing minor punch list items in the process area. Crew members will be working at various off-facility vault and panel locations during testing operations.  

As always, if anyone has any questions about these construction activities, please give me a call at 941-554-3862 or 1-800-449-4486 and I’ll do my best to get the appropriate answers to your questions. 

02-01-13-1525-well-penetration-southwest-portion-of-treatment-building-cw

01-28-13-1603-positive-verification-of-ew-4007-level-cw

02-01-13-1540-holes-in-soffit-northeastern-soffit-line-cw

02-01-13-0902-rc7002-final-inspection-jv

01-28-13-1520-view-out-of-loading-dock-cw

01-28-13-1329-type-em-light-fixture-positive-verification-cw

02-01-13-1525-eastern-site-overview-cw

01-31-13-1256-ew4007-final-inspection-jv

02-01-13-1555-process-area-overview-cw

01-31-13-1117-mh49-no-spring-assist-on-lid-final-inspection-jv

gary-4

Gary Cambre                                                                                  Public Affairs         Sr. Communications Manager                                                     


01-28-13-1340-eastern-site-overview-cw