Equipment and Operations Being Tested and Double-Checked


02-20-13-1236-southwest-gutter-installed-cw

Friday, March 1,2013

Equipment and Operations Being Tested and Double-Checked

 

The testing of process equipment and instrument communications systems continued at the Lockheed Martin facility this week in preparation for operations startup.

Minor punch list items at the well vaults were being addressed by field crews to verify operational readiness. At the building, crews continued installing protective bollards at the south end of the building, and they also addressed electrical and process area punch lists.

Next week, pre-startup activities will continue and crew members will work at various off-facility vault and panel locations during testing operations. Operational readiness review activities and meetings will continue to be held prior to startup.

As always, if anyone has any questions about these construction activities, please give me a call at 941-554-3862 or 1-800-449-4486 and I’ll do my best to get the appropriate answers to your questions.

 

02-19-12-1508-haz-com-sign-in-place-at-confined-space-02-el

02-21-13-1544-zip-tied-wire-on-cip-skid-cw


02-19-12-1507-overview-of-various health-and-safety-safeguards-in-the-process-area-01-el

02-21-13-1543-zip-tied-profibus-cable-on-ro-system-cw

02-20-13-1305-wwf-for-site-civil-concrete-pour-cw

02-19-12-1507-overview-of-tank-access-ladder-01-el

02-21-13-1544-zip-tied-profibus-cable-on-ro-system-cw

02-19-12-1505-fire-extinguisher-and-fire-pull-box-in-place-01-el

gary-4

Gary Cambre                                                                                  Public Affairs         Sr. Communications Manager                                                     

02-21-13-1519-southwest-gutter-installed-cw