Preparation Continuing Toward Operations Startup Goal


DSC00990

Friday, March 8, 2013

 
Preparation Continuing Toward Operations
Startup Goal

Extensive testing is part of the preparation for operations startup of the water treatment system at the Lockheed Martin facility.  Our crews continued their work this week to test process equipment and instrument communications systems.

Crews also continued addressing minor punch list items at off-facility control panels and well vaults to verify operational readiness. In the building, crews worked on minor painting and electrical punch list items.

Next week, pre-start-up testing will continue with operator training and functional checkout of process equipment. Off-facility well pump operational testing will be conducted. Crew members will work at various off-facility vault and panel locations during testing activities. Operational readiness review activities and meetings will continue.

Extensive testing is part of the preparation for operations startup of the water treatment system at the Lockheed Martin facility.  Our crews continued their work this week to test process equipment and instrument communications systems.

As always, if anyone has any questions about these construction activities, please give me a call at 941-554-3862 or 1-800-449-4486 and I’ll do my best to get the appropriate answers to your questions. 

DSC00957

DSC00998

DSC00962

DSC00983

DSC00975

DSC00970

DSC00969

DSC00964

DSC00978

gary-4

Gary Cambre                                                                                  Public Affairs         Sr. Communications Manager                                                     

DSC00971