Punch List Items Being Addressed at Vault Locations and Facility


DSC01006

Friday, March 15, 2013

Punch List Items Being Addressed at Vault Locations and Facility

 

Crews continued this week to address minor punch list items at the well vaults to verify operational readiness, and then pursued operational testing of the off-facility wells. At the water treatment building on the Lockheed Martin site, crews addressed minor punch list items in the process area, and in the office area, including final touch up painting. 

Next week, pre-startup activities will continue and crew members will work at various off-facility vault and panel locations during extraction well testing operations. Operational readiness review activities and meetings will continue to be held prior to startup.

As always, if anyone has any questions about these construction activities, please give me a call at 941-554-3862 or 1-800-449-4486 and I’ll do my best to get the appropriate answers to your questions.

DSC01021

DSC01020

DSC01005

DSC01002

03-05-13-1331-northern-header-overview-cw

DSC01012

DSC01014

03-06-13-1542-aop-unit-panel-cw

DSC01016

DSC01017

DSC01008

DSC01000

gary-4

Gary Cambre                                                                                  Public Affairs         Sr. Communications Manager                                                     

DSC01011