Training and Testing Continue Toward System Startup


DSC01036

Friday, March 22, 2013

 
Training and Testing Continue Toward System Startup

 

Treatment system operator class room training continued this week as crews prepared for the water treatment facility system startup.  At the off-facility well sites, operational testing was also conducted for the effort.  Minor punch list items in the building and at the well vaults were also addressed in order to verify operational readiness.

Next week, operational readiness meetings will be held and pre-system startup activities will continue. Crews will continue to work at various off-facility vault and panel locations during pre-system startup activities.

As always, if anyone has any questions about these construction activities, please give me a call at 941-554-3862 or 1-800-449-4486 and I’ll do my best to get the appropriate answers to your questions. 

DSC01037

DSC01049

DSC01025

DSC01024

02-11-13-1426-vent-piping-northern-process-area-cw

DSC01031

DSC01046

02-11-13-1429-southeastern-process-area-overview-cw

02-12-13-1708-photocat-unit-overview-cw

DSC01028

DSC01033

DSC01030

DSC01026

gary-4

Gary Cambre                                                                                  Public Affairs         Sr. Communications Manager                                                     

DSC01026