Site Improvements Being Completed


DSC01075

Friday, April 5, 2013

 
 

Site Improvements Being Completed

Lots of site improvements are being completed on the Lockheed Martin site.  This week crews finished putting down the artificial turf on asphalt areas.  A dumpster enclosure was completed and overall landscaping was finished.  Work also began on the motorized gate operation.

Work also continued this week with pre-system startup activities at various off-facility vault and panel locations.  Operator class room training also continued.

Next week, work on the fencing along Tallevast Road will continue, and the final paint coating will be applied to the perimeter walls.  Operational readiness meetings will be held and pre-system startup activities will continue. Crews will continue to work at various off-facility vault and panel locations during pre-system startup activities.

As always, if anyone has any questions about these construction activities, please give me a call at 941-554-3862 or 1-800-449-4486 and I’ll do my best to get the appropriate answers to your questions. 

01-15-13-1106-process-area-overview-cw

DSC01024

02-19-12-1508-haz-com-sign-in-place-at-confined-space-02-el

02-19-12-1507-overview-of-various health-and-safety-safeguards-in-the-process-area-01-el

02-20-13-1236-southwest-gutter-installed-cw

DSC00971

DSC01057




gary-4

Gary Cambre                                                                                  Public Affairs         Sr. Communications Manager                                                     

DSC01052