Gary Cambre Public Affairs Sr. Communications Manager
Tallevast
- Tallevast & Lockheed Martin
- Environmental Testing & Cleanup
- Community Programs & Events
- Contact Us
- News & Information
-
Tallevast Blog
- Tallevast Blog Archive
- Construction Activities Moving Forward
- System Testing and Detail Work Continues
- Lots of Testing in Preparation of Facility Completion
- Work Continuing on Pre-System Startup Operations
- Pre-System Startup Operations in Process
- Training and Testing for Operational Readiness
- Equipment and Operations Being Tested and Double-Checked
- Preparations Continuing Toward Operations Startup Goal
- Punch List Items Being Addressed at Vault Locations and Facility
- Training and Testing Continue Toward System Startup
- Operational Readiness Continues
- Site Improvements Being Completed
- Pre-System Startup Activities Continue
- Training and Preparation Activities Work Toward System Startup
Construction Work to Shutdown for the Holidays
![]() |
![]() |
Friday, December 21, 2012
Construction Work to Shutdown for the Holidays
Construction work on the water treatment facility will shutdown for the holidays beginning Monday, Dec. 24 through New Years Day – Tues., Jan. 1, 2013. Work will resume on Jan. 2, 2013.
This week, crews began preparations to demobilize for the holidays. Building crews placed activated carbon into the granular activated carbon (GAC) units, performed maintenance on the filters and water softeners, and applied the epoxy floor coating in the process area. Crews also continued instrument configuration, metal walkway installation, electrical wiring testing, plumbing, mechanical, painting, tile, and stucco punch list work.
In the field, conveyance piping crews continued assembling and installing pumps and hardware in the wells and vaults, pulling wiring, and pressure testing conveyance lines. On the Schmid Farm, FP&L installed transformers to power off-site wells, and work began to install fencing compounds around control panels and well vaults.
Upon returning to work on January 2nd, crews will continue testing process equipment, communications and wiring. Contractors will address building punch list items, including painting, trim, mechanical and stucco. Contractors will install aluminum walkways and handrails within the process area.
In the field, contractors will continue installing the remaining well heads and pumps and wiring at the off-site structures. Fencing work on the Schmid Farm will continue. Personnel will also be programming and performing work at off-site control panel locations. Contractors will continue removing unused and excess equipment and materials from the site. Various transportation vehicles will be transporting material off site for proper disposal, as required.
We wish everyone a very Merry Christmas and Happy Holiday Season…and as always, if anyone has any questions about these construction activities, please give me a call at 941-554-3862 or 1-800-449-4486 and I’ll do my best to get the appropriate answers to your questions.





















